ARRA REPORTING - Housing Project Management
| ARRA Housing Project Manager |
|
GOAL: The creation of the Housing Project Manager position allows Community Action to expand our affordable housing development activities. This position will oversee the completion of 12 projects; home improvements to 7 low-income owner occupied properties in Walworth County, facilitate the purchase and rehabilitation of two affofordable rental projects in Rock County; and rehabilitate 3 homes in Beloit's Merrill Housing Initiative for sale to low-income owner occupants.
View Full Report Back to ARRA Programs
|
| ARRA Financing |
| |
May 1- Sept. 30, 2009 |
Oct.1-Dec. 31, 2009 |
Jan. 1-March 31, 2010 |
April 1-June 30, 2010 |
July 1 - Sept. 30, 2010 |
| Budgeted Funds |
$78,000 |
$55,864 |
$42,760 |
|
|
| Funds Expended |
$22,136 |
$13,104 |
|
|
|
| |
|
|
|
|
|
| ARRA Job Creation Outcomes |
| |
May 1-Sept. 30, 2009 |
Oct. 1-Dec. 31, 2009 |
Jan. 1-March 31, 2010 |
April 1 - June 30, 2010 |
July 1 - Sept. 30, 2010 |
| Jobs Created or retained by CAI |
1 |
.86 |
|
|
|
| |
|
|
|
|
|
| ARRA Program Activity Outcomes |
| |
May 1-Sept. 30, 2009 |
Oct. 1-Dec. 31, 2009 |
Jan. 1 - March 31, 2010 |
April 1- June 30, 2010 |
July 1 - Sept. 30, 2010 |
Number of Walworth County low-income home improvement projects completed
(Goal 7) |
1 |
3 |
|
|
|
Number of affordable rental housing projects completed through purchase and rehabilitation
(Goal 2) |
0 |
0 |
|
|
|
Number of homes rehabilitated in the Merrill neighborhood for sale to owner-occupants
(Goal 3) |
0 |
1 |
|
|
|
| |
|
|
|
|
|
| Program Milestones |
| ARRA Plans & Targets |
May 1-Sept. 30, 2009 |
Oct. 1-Dec. 31, 2009 |
Jan 1.- March 31, 2010 |
April. 1 - June 30, 2010 |
July 1 - Sept. 30, 2010 |
| |
The Housing Project Manager spent significant time assisting with Summer Youth Employment Project in the first Quarter. |
Work currently underway on two separate Rock County purchase/rehab-rental projects (1417 and 1423 Hull). 4 Walworth County Home Projects have been completed.
(1) Merrill Housing Project at 1352 is complete and home is being marketed for sale to low-income household.
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|